ENERTEC MADA
Projet Solaire Ambatolampy 20 MW 20/63KV, Madagascar


Points forts du projet
- Localisation : Ambatolampy; Madagascar
- Capacité : 20 MW
- Calendrier : Aug 2022 – April 2023
-
Nos Services EPC Intégrés
- Revue de la conception technique
- ITravaux civils
- Assemblage et installation des appareillages et équipements de la sous-station 22/63 kV
- Installation des équipements électriques
- Travaux DC, basse tension (BT) et moyenne tension (MT) du projet
- Travaux sur ligne aérienne 63 kV
- Tests de l’installation ; mise en service à froid et à chaud
- IMise à jour des plans d’ingénierie (redlining)
 Amabatolampy 40MW Solar Power Plant Areal Photo 1.jpg)
 Arial Photo - Ambatolampy 40MW Solar Power Plant 2.jpg)
 22-63KV Substation Installation Works Completed and Energized.jpg)
 Clearing of 22-63KV Substation Terrian.jpg)
 Substation Topsoil Removal in Progress.jpg)
 Substation Access Road Works in Progress.jpg)
 Substation Earth Matt Excavation.jpg)
 Substation Earth Matt Installation 1.jpg)
 Substation Earthing Matt Installation 2.jpg)
 Earth Matt Installation.jpg)
 Earth Matt Installation 3.jpg)
 Earth Matt Exothermic Welding Preparation.jpg)
 Earth Matt Exothermic Weld Connection 1.jpg)
 Erath Matt Exothermic Weld 2.jpg)
 Materials Preparation.jpg)
 Steel Structure Earthing Installation.jpg)
 Construction Works in Progress.jpg)
 Site Works Inspection.jpg)
 Delivery of Off-Road 4x4 Crane on Project Site.jpg)
 Substation Steel Structure Assembly, Erection and Installation.jpg)
 Substation Steel Structure Assembly, Erection and Installation.jpg)
 Substation Steel Structure Assembly, Erection and Installation.jpg)
 Substation Steel Structure Assembly, Erection and Installation.jpg)
 Steel Structures Assembly, Erection and Installation.jpg)
 Steel Structures Assembly, Erection and Installation.jpg)
 Preparing off-loading of 20MVA Transformer and Components.jpg)
 Positioning of 63-22KV Transformer on Concrete Base.jpg)
 20MVA Transformer and Components delivered On-site.jpg)
 20MVA Transformer and Components Unpacking.jpg)
 Offloading Project Material.jpg)
 63-22KV Transformer Assembly.jpg)
 20MVA Transformer Assembly in Progress.jpeg)
 20MVA Transformer Assembly in Progress.jpeg)
 20MVA Transformer Assembly in Progress.jpeg)
 20MVA Transformer Assembly in Progress.jpeg)
 20MVA Transformer Assembly in Progress.jpeg)
 20MVA Transformer Testing.jpeg)
 9 Meter Steel Tower - Installation.jpg)
 9 Meter Steel Tower - Prepare to Lift.jpg)
 Meter Substation Steel Structure Assembly.jpg)
 Prepare 63KV Line Isolators for Installation.jpg)
 63KV VT Installation.jpg)
 Installation and Calibrationof 63KV Line Isolator Mechanism.jpg)
 Installation of 63KV Line Isolators + VTs & CTs in progress.jpg)
 Installation of 18 meter Lightning Mast in Progress.jpg)
 Site Meeting.jpg)
 Sleeves and Cable Installation.jpg)
 Sleeves and Cable Installation.jpg)
 Sleeves and Cable Installation.jpg)
 Cable Terminations.jpg)
 Cable Installation.jpg)
 63KV VT Cable Rack and Cable Works.jpg)
 63KV CT Wiring.jpg)
 Cable Installation.jpg)
 Cable Installation Works.jpg)
 - 20KV Cable Installation in Progress.jpg)
 Cable Installation in Progress.jpg)
 Temporary protection agains the Elements.jpg)
 Cable Installation in Progress.jpg)
 Cable Rack Installation.jpg)
 Transfrormer Cable Rack and Cable Installation.jpg)
 Continarized Substation Delivery on-site.jpg)
 Containerized Substation Installation.jpg)
 22KV Schneider Switchgear Installation.jpg)
 - 20KV Cable Termination in Substation.jpg)
 Substation Airconditioning Installation 1.jpg)
 Airconditioner Installation 2.jpg)
 Substation Panel Wiring.jpg)
 Substation Panel Wiring - Fault Finding and Repair Works.jpg)
 Panel Wiring in Progress.jpg)
 MV Cable terrminations.jpg)
 SCADA Wiring 1.jpg)
 SCADA Wiring 2.jpg)
 SCADA Wiring 3.jpg)
 SCADA Works in Progress.jpg)
 Tropical Storm during Construction Phase.jpg)
 Tropical Storm during Construction Phase.jpg)
 63KV Overhead Line - Steel Structure Assembly.jpg)
 63KV Overhead Line - Install Concrete Blocks for H-Pole Structure in Pond.jpg)
 63KV Overhead Line - Install Concrete Blocks for H-Pole Structure in Pond.jpg)
 63KV Overhead Line - Lifting of Steel Towers in Progress.jpeg)
 63KV Overhead Line - Install Concrete Blocks for H-Pole Structure in Pond.jpg)
 63KV Overhead Line Construction.jpg)
 63KV Overhead Line Stringing 1.jpg)
 63KV Overhead Line Stringing 2.jpg)
 63KV Overhead Line Stringing Completed.jpg)
 Project Construction Status Photo.jpg)
 Safety First! - Housekeeping 1.jpg)
 Safety First! - Housekeeping 2.jpg)
 Safety First! - Morning Toolbox Talk.jpg)
 Plant Cold Commisioning.jpg)
 Plant Hot Commissioning.jpg)
 Panel Wiring Fault Finding and Repairs in Substation.jpg)
 Schneider Switchgear Panel Wiring 1.jpg)
 Schneider Switchgear Panel Wiring in Progress.jpg)
 Schneider Switchgear Panel Wiring.jpg)
 Field Communication Equipment Wiring.jpg)
 Panel Wiring in Substation.jpeg)
 Panel Wiring in Substation.jpg)
 Panel Wiring for Substation.jpg)
 SCADA Works inProgress.jpg)
 Fire Alarm Installation.jpg)
 DC Battery Charger Fault Finding and Repairs 1.jpg)
 DC Battery Charger Repaired 2.jpg)
 Field Communication Cable Installation.jpg)
 LV AC Sleeves and Cable Installation.jpg)
 LV AC Sleeves and Cable Installation.jpg)
 LV AC Sleeves and Cable Installation.jpg)
 LV AC Cable Terminations in Progress.jpg)
 Torquing of LV AC Minisub Connections.jpg)
 MinisubLV AC Terminations to Inverter.jpg)
 Substation SwitchroomLights Installation.jpg)
 63KV CT Cable Installation and Terminations.jpg)
 LV Control Box Wiring in Progress.jpg)
 LV Control Panel Cable Rack and Cable Installation.jpg)
 LC Cable Rack and Cable Installation Works in Progress.jpg)
 .Transfrormer Cable Rack and Cable Installation.jpg)
 Earthing and Steel Works.jpg)
 Earthing Works and Steel Works.jpg)
 Earthing Exothermic Weld 1.jpg)
 Earthing Exothermic Weld 2.jpg)
 MECHANICAL - Steel Structure Assembly.jpg)
 MECHANICAL - Steel Structure Assembly.jpg)
 MECHANICAL - Steel Structure Assembly and Installation.jpg)
 MECHANICAL - Assembly and Installation of Steel Structures.jpg)
 MECHANICAL - Steel Structures Assembly 1.jpg)
 MECHANICAL - Steel Structure Assembly 2.jpg)
 MECHANICAL - 18 Meter Lightning Mast.jpg)
 MECHANICAL - Install 18 Meter Lightning Mast.jpg)
 MECHANICAL - Cable Racking Installation.jpg)
 4x4 Off-Road Crane.jpg)
 63KV Overhead Line Construction.jpg)
 63KV Overhead Line Stringing 2.jpg)
 LV AC Cable installation - Transformer to Inverters.jpg)
 MV Cable Installation.jpg)
 22KV Cable Joint in Progress.jpg)
 22 KV Cable Joint Completed.jpg)
 Minisub MV Cable Termination Works in Progress.jpg)
 Transformer MV Cable Termination.jpg)
 MV Cable Termination.jpg)
 11KV Equipment Installation and Cable Termination for MV Motor.jpg)
 22KV Schneider Switchgear Busbar Assembly and Installation.jpg)
 MV Cable Termination Works in Progress.jpg)
 Install 6.6KV Accessories in MV Motor and Connect Electrically.jpg)
 CIVIL Works 2.jpg)
 CIVIL Works 3.jpg)
 Racking and Cable Installation.jpg)
 Airconditioning Installation.jpg)
 Airconditioner Installation 2.jpg)
 Site Construction Works in Progress.jpg)
 Safety First! - Housekeeping 1.jpg)
 Safety First! - Housekeeping 2.jpg)
 Safety First! On-site Morning Safety Toolbox Talk.jpg)